Loan to cost (LTC) is a real estate lending ratio that measures the loan against the total cost of a project. It is not the same as loan to value, because the denominator is cost rather than appraised value. Lenders use it on fix-and-flip, bridge, construction, and value-add deals to limit how much of the project they fund.

Total cost includes the purchase price, the rehab budget, closing costs, carrying costs, and any reserves the lender requires. A lender that caps LTC at 75% will fund $75 of every $100 of project cost, and the borrower supplies the other $25. That cap is an example used throughout this article, not a quoted market maximum.

How do you calculate loan to cost?

Divide the loan amount by total project cost, then multiply by 100 to express the result as a percentage. The order matters: the loan goes on top, and the full cost goes on the bottom.

LTC = loan amount ÷ total project cost × 100

Step 1: Add up total project cost

Start with the purchase price and add the rehab budget, closing costs, carrying costs, and any required reserves. Use the lender’s cost worksheet if one is available, because some programs count financed fees and interest reserves in the cost total.

Step 2: Confirm the loan amount

Use the loan amount the lender will actually fund, not the purchase price. If the loan includes financed points or fees, the funded amount can be higher than the base loan.

Step 3: Divide loan by cost

Run the arithmetic on the full cost, not on the purchase price alone. For example, a $250,000 purchase, $50,000 rehab, $10,000 closing costs, and $5,000 carrying costs total $315,000. A $236,250 loan divided by $315,000 is 0.75, or 75% LTC.

Step 4: Compare with the lender’s maximum

Compare the result with the lender’s cap and with your own cash reserve. A deal at the cap has no room for a cost overrun unless you hold cash outside the project.

What costs go into total project cost?

Total project cost includes every dollar needed to buy and finish the property, not just the purchase price.

Purchase price, rehab labor and materials, permits, closing costs, loan fees, property taxes and insurance during the work, and utility bills all belong in the cost total. A contingency line for overruns is part of a realistic budget even when the lender does not require it.

Lenders may treat some costs differently. One lender might count a financed origination fee in total cost, while another leaves it out. Ask for the cost breakdown before comparing LTC caps, because a lower cap on a broader cost base can produce a larger loan.

A detailed scope of work matters more than a round rehab estimate. The guide to how fix and flip loans work explains how draws and interest reserves affect the cash you need.

How is loan to cost different from loan to value?

LTC uses total project cost as the denominator. LTV uses the property’s appraised value or purchase price, whichever is lower in most mortgage underwriting.

MeasureFormulaExample
LTCloan ÷ total project cost$236,250 ÷ $315,000 = 75.0%
LTV at purchaseloan ÷ purchase price$236,250 ÷ $250,000 = 94.5%
LTV at after-repair valueloan ÷ ARV$236,250 ÷ $400,000 = 59.1%

The table shows why a deal can look safe on LTC and tight on LTV before the work is finished. The property may not appraise at the after-repair value until the rehab is complete. Lenders often underwrite both ratios and use the lower result when setting the loan.

The guide to loan to value ratio covers the LTV side in more detail. It also explains why a low LTV after repair does not help if the lender will not fund the rehab upfront.

What is a good loan-to-cost ratio?

A lower LTC leaves a larger cash cushion for cost overruns, delays, and a weaker resale price. There is no single good number because lenders set caps by program, property type, and borrower experience.

Assumed LTC capLoan on $315,000 costBorrower cashWhat it leaves
65%$204,750$110,250larger cushion
75%$236,250$78,750moderate cushion
85%$267,750$47,250thin cushion

At 85%, a $30,000 overrun would use most of the $47,250 cash cushion, leaving $17,250. At 65%, the same overrun leaves $80,250. The ratio does not predict the overrun, but it shows how much room the borrower has before the deal needs more cash.

A borrower with a strong reserve can accept a higher cap. A borrower using most of their cash at closing should prefer a lower one, because the first cost overrun otherwise becomes a financing problem.

LTC is not a substitute for the 70% rule, which starts from after-repair value. The guide to the 70% rule in real estate shows how to set a maximum offer from ARV.

How does loan to cost affect the cash you need?

Cash needed at closing is total project cost minus the loan amount, plus any costs the lender does not finance.

On the $315,000 project, a 75% LTC loan of $236,250 leaves $78,750 for the borrower to fund. If closing costs or reserves are paid outside the loan, add those to the cash figure.

The ratio also changes when the cost changes. A $20,000 rehab overrun raises total cost to $335,000.

At a 75% cap, the loan could rise to $251,250, but only if the lender approves the higher budget. Otherwise the borrower funds the $20,000 and the LTC on the original loan falls.

Short-term lenders price by risk and LTC. The guide to how hard money loans are priced explains the trade-off between rate, points, and loan size.

How does a bridge loan fit into loan to cost?

A bridge loan can fund part of a project while a sale or refinance is pending. Its interest, points, and fees belong in the cost side if the lender counts them.

A bridge loan example: $300,000 at 9% for 12 months with 1.5 points and $2,000 of other fees has $27,000 of interest, $4,500 of points, and a $33,500 borrowing cost. The total due at the end is $333,500 because the $300,000 balance is a balloon.

If the lender lets the borrower finance that $33,500, the loan grows and the LTC rises. If the borrower pays it from cash, the cash requirement rises instead. The guide to bridge loans explained covers the balloon math.

What are common mistakes in loan-to-cost math?

Most errors come from using the wrong cost base or treating the ratio as a profit test.

  • Using the purchase price as total project cost. It leaves out rehab, closing costs, and carrying costs, so the LTC looks lower than it is.
  • Forgetting the contingency. A rehab budget without an overrun line can force the borrower to stop work or add cash.
  • Comparing caps without comparing definitions. Two lenders can count different fees, which changes both the loan amount and the ratio.
  • Treating the loan as the cost. The loan is the numerator; the cost is the denominator.
  • Assuming a low LTC guarantees a profit. The exit price and the rehab timeline still decide the result.